title: "Palo Alto ADU permit process: steps and fees"
description: "Step-by-step Palo Alto ADU and JADU permit process: lot check, pre-approved plans, submittal, the 60-day state limit, FY2027 fees and deed rules."
url: https://bayarearebuild.com/palo-alto/adu-permit-process
last_checked: 2026-11-19
---

[Home](https://bayarearebuild.com/) / [Palo Alto](https://bayarearebuild.com/palo-alto/) / [ADUs](https://bayarearebuild.com/palo-alto/adu/) / ADU permit process

Palo Alto · ADU and JADU permits

# The Palo Alto ADU permit process, step by step

Building an ADU in Palo Alto takes nine steps from the lot check to move-in. Under state law the city has 15 business days to decide if an application is complete and 60 days to approve or deny it; own ADU permits opened since Nov 2021 took a median 506 days from application to final inspection. Data last checked 2026-11-19.

- **9**: steps from lot check to move-in
- **15 bus. days**: to decide if the application is complete
- **60 days**: to approve or deny a complete application
- **$7,346**: detached ADU building permit (no master plan)
- **< 750 sf**: no city impact fees
- **506 days**: median application to final, own ADU permits

## Nine steps to a permitted ADU

For a typical ADU or JADU on a single-family lot. The phase lengths are the city guidebook's ranges[1]; the 15-day and 60-day limits are state law[9].

1. ### Check that your lot qualifies and pick an ADU type
   - **Who:** Owner
   - **Published timing:** Guidebook planning phase: 1 to 3 months[1]
   - **Published fees:** none
   - ADUs are allowed on any lot where single- or multi-family housing is permitted; check the zone with our [ADU lookup](https://bayarearebuild.com/palo-alto/adu/#lookup) or the city's Property Information Map.[1,2]
   - Choose detached, attached, conversion or JADU. The state-guaranteed detached ADU is up to 800 sf, 16 ft and 4 ft from side and rear lines; city ADUs go up to 900 or 1,000 sf.[1,3]
   - Flood zone, historic district or historic-resource lots can have extra building and design requirements.[1]
   - The Planner on Duty takes virtual and in-person appointments at the Development Center, 285 Hamilton Avenue, (650) 617-3117, Planner@CityofPaloAlto.org.[1]
2. ### Choose a design: pre-approved, master plan or custom
   - **Who:** Owner, architect or designer, prefab company
   - **Published timing:** Guidebook design phase: 2 to 6 months[1]
   - **Published fees:** Master permit $2,653; site-specific permit related to a master $3,929 (prefab) or $5,481 (site-built)[4]
   - The city ADU Plans Gallery lists four pre-approved plans (343 to 716 sf). Pre-approved means already reviewed for building code; site planning and other applications are still required.[5]
   - Designers can file a master permit for a detached ADU design under the address 250 Hamilton Avenue; each lot then gets a site-specific permit.[6,4]
   - Detached ADUs must meet CALGreen Mandatory plus Tier 2 (sheet GB-1) per the master checklist.[6]
3. ### Prepare the permit set
   - **Who:** Architect or designer, engineer
   - **Published timing:** Included in the design phase
   - **Published fees:** not published
   - The plan set covers architectural plans (floor, roof, elevations, sections, window and door schedules), structural plans and calculations, electrical, mechanical and plumbing plans, CALGreen forms and Title 24 energy forms.[6]
   - Trees: every development project submits the T-1 tree disclosure sheet; for ADU-only projects it does not have to be completed by a certified arborist.[7]
   - Utilities: apply for new or upgraded electric, gas and water service with City of Palo Alto Utilities.[8]
4. ### Submit online and pass the completeness check
   - **Who:** Owner or designer, Project Coordinator
   - **Published timing:** Completeness decision within 15 business days, or the application is deemed complete[9]
   - **Published fees:** Paid in steps; see below
   - All applications, plans and documents are submitted electronically through Accela Citizen Access (ACA).[6,10]
   - If the application is incomplete, the city must list the missing items and explain how to complete it.[9,11]
5. ### Plan check and the 60-day decision
   - **Who:** City plan reviewers
   - **Published timing:** 60 days to approve or deny a complete application when a home already exists on the lot; otherwise deemed approved[9]. Guidebook permitting phase: 1 to 2 months[1]
   - **Published fees:** Building permit fees below
   - ADUs and JADUs are approved ministerially, without a public hearing, using objective standards only.[11]
   - If the ADU is filed together with a new home, the city may wait to act on the ADU until it acts on the new home; the clock stops if the applicant asks for a delay.[9]
   - Respond to plan-check comments and resubmit if needed; then pay outstanding fees and receive the permit.[1]
6. ### Pay fees
   - **Who:** Owner
   - **Published timing:** Fees are due when the application is converted to a permit[10]
   - **Published fees:** See the fee table
   | Fee (City of Palo Alto, FY 2027 unless noted) | Amount |
   |---|---|
   | Building permit, stand-alone detached ADU (not using a master plan) | $7,346 per permit |
   | Master permit for a stand-alone detached ADU design | $2,653 per permit |
   | Site-specific permit related to a master: prefab / site-built | $3,929 / $5,481 per permit |
   | Building permit fees, range given in the 2025 guidebook | $2,000 to $8,000 |
   | Development impact fees: ADUs under 750 sf, JADUs, garage conversions with no added floor area | Exempt |
   | Development impact fees: ADUs 750 sf and over (proportional to the main home); guidebook range | $10,000 to $80,000 |
   | Impact fee rates the proportional fee is based on (single family): parks; community center; library | $18.75; $1.44; $0.86 per sf |
   | Impact fee rates (single family): public safety; general government | $1,383; $1,743 per unit |
   | PAUSD school fee (not for JADUs or ADUs under 500 sf) | $4.79 per sf |
   | Utility connection fees | not published (set by City of Palo Alto Utilities) |
   Sources: ADU building fees[4]; impact fees and exemptions[12,13]; guidebook ranges and school-fee note[1]; school fee[14]. How the city prorates the impact fee for an ADU of 750 sf or more is not published as a formula.
7. ### JADU only: record the deed restriction
   - **Who:** Owner, planner, notary
   - **Published timing:** Before the JADU permit is finaled
   - **Published fees:** not published
   - A JADU needs a deed restriction stating that it cannot be sold separately from the main home and limiting its size and features; the owner must live in the main home or the JADU.[1]
   - The city process: the owner signs the agreement before a notary, the city signs it, it is recorded with the Santa Clara County Recorder, and the planner uploads the recorded copy to the permit in Accela.[15]
8. ### Hire a contractor and build
   - **Who:** Owner, licensed contractor
   - **Published timing:** Guidebook: bidding 1 to 3 months, construction 6 to 12 months[1]
   - **Published fees:** Included in the building permit fee
   - Request and compare bids, then sign a contractor; check any license with the CSLB.[1,16]
   - The contractor calls for inspections as required, ending with final inspection approval.[1]
9. ### Final inspection, then rent or move in
   - **Who:** Contractor, Building Division
   - **Published timing:** Measured: median 506 days (17 months) from application to final for 176 finaled ADU/JADU permits opened since Nov 2021[17]
   - **Published fees:** not published
   - Rentals must be for 30 days or more.[1]
   - Property taxes: the main home is not reassessed, but taxes rise based on the value of the ADU.[1]

## How long ADU permits are taking now

Measured, not published: the city does not publish a typical ADU review time, so we calculate it daily from the city's own permit records.

| Permit type | Permits issued | Average days | Median days |
|---|---|---|---|
| ADUs | 13 | 252 | 204 |
| JADUs | 3 | 212 | 223 |

Calculated by Bay Area Rebuild from City of Palo Alto permit data[18,20,19]: calendar days from application (date the permit was opened) to issuance, for permits issued Aug 22, 2026 to Nov 19, 2026 (rolling 90 days, updated daily). Includes the applicant's time to respond to plan-check comments; it is not a city target or a promise. Last updated Nov 19, 2026.

[Recently approved ADUs and JADUs](https://bayarearebuild.com/palo-alto/adu/#approved)

## Frequently asked questions

**### How long does Palo Alto take to approve an ADU?**

By state law the city has 15 business days to decide whether an ADU application is complete and 60 days to approve or deny a complete application when a home already exists on the lot. The city guidebook puts the permitting phase at 1 to 2 months.[9,1]

**### What does an ADU building permit cost in Palo Alto?**

For FY 2027 the building permit for a stand-alone detached ADU that does not use a master plan is $7,346. A site-specific permit related to a master plan is $3,929 for prefab or $5,481 for site-built.[4]

**### Do I need a hearing or neighbor approval for an ADU?**

No. ADUs and JADUs are approved ministerially, without discretionary review or a hearing, using objective standards.[11]

**### Does a JADU need anything extra?**

Yes. A JADU needs a recorded deed restriction and owner occupancy of the main home or the JADU.[1,15]

**### How long are Palo Alto ADU permits taking right now?**

Measured from city permit data: 16 permits issued Aug 22, 2026 to Nov 19, 2026 took an average of 245 days and a median of 208 days from application to issuance. These are calendar days, including time the applicant spends on plan-check corrections.[18,19]

## What the city does not publish

- A typical plan-check review time for ADUs (we show measured times above).
- Utility connection fees for an ADU as a fixed amount.
- The formula for the proportional impact fee on ADUs of 750 sf or more.

We do not fill these gaps with estimates. Ask the Planner on Duty at (650) 617-3117.[1]

## Sources and last-checked dates

1. [City of Palo Alto: J/ADU Guidebook 2025 (PDF; ADU types, eligible zones, state and city standards, fees overview, timeline, FAQ)](https://www.paloalto.gov/files/assets/public/v/1/planning-amp-development-services/adu_jadu-handbook-2025.pdf)
   City of Palo Alto · last checked 2026-11-19
2. [City of Palo Alto ArcGIS: AssessorsParcels layer (zone, lot size, city-computed FAR, coverage, setbacks, height, flood and historic flags)](https://services6.arcgis.com/evmyRZRrsopdeog7/arcgis/rest/services/AssessorsParcels/FeatureServer/0)
   City of Palo Alto GIS · last checked 2026-11-19
3. [Palo Alto Municipal Code 18.09.030 (state-exempt ADUs/JADUs, Table 1)](https://codelibrary.amlegal.com/codes/paloalto/latest/paloalto_ca/0-0-0-76738)
   American Legal (official online code) · last checked 2026-11-19
4. [City of Palo Alto: FY 2027 Adopted Municipal Fee Schedule, Development Services building fees incl. ADU master-plan fees (PDF p. 67)](https://www.paloalto.gov/files/assets/public/v/1/administrative-services/city-budgets/municipal-fee-schedules/fy-2027-adopted-municipal-fee-schedule.pdf)
   City of Palo Alto · last checked 2026-11-19
5. [City of Palo Alto ADU Plans Gallery (ADU Accelerator / Community Planning Collaborative)](https://cityofpaloalto.aduaccelerator.org/gallery)
   ADU Accelerator for the City of Palo Alto · last checked 2026-11-19
6. [City of Palo Alto: Master ADU permit submittal checklist (2026, PDF)](https://www.paloalto.gov/files/assets/public/v/3/development-services/building-permits/0.-building-permit-submittal-forms/master-adu-checklist-2026.pdf)
   City of Palo Alto · last checked 2026-11-19
7. [City of Palo Alto Urban Forestry: Tree Ordinance Information (protected trees, T-1 tree disclosure)](https://www.paloalto.gov/Departments/Public-Works/Public-Services/Palo-Altos-Urban-Forest/Tree-Ordinance-Information)
   City of Palo Alto · last checked 2026-11-19
8. [City of Palo Alto Utilities: New Connection or Upgrades to Utilities](https://www.paloalto.gov/Departments/Utilities/Utilities-Services-Safety/New-Connection-or-Upgrades-to-Utilities)
   City of Palo Alto · last checked 2026-11-19
9. [California Government Code § 66317 (ADU permit: 15 business days for completeness, 60 days to approve or deny, deemed approved)](https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66317.)
   California Legislative Information (official text; read via search index, site blocks automated fetch) · last checked 2026-11-19
10. [City of Palo Alto: Apply for a Building Permit](https://www.paloalto.gov/Departments/Planning-Development-Services/Development-Services/Start-the-Permit-Process/Apply-for-a-Building-Permit)
   City of Palo Alto · last checked 2026-11-19
11. [California HCD: Accessory Dwelling Unit Handbook, updated March 2026 (PDF)](https://www.hcd.ca.gov/sites/default/files/docs/policy-and-research/ADU-Handbook-Update.pdf)
   State of California · last checked 2026-11-19
12. [City of Palo Alto: Development Impact and In-Lieu Fees, as of Aug 17, 2026 (PDF)](https://www.paloalto.gov/files/assets/public/v/5/development-services/planning-review/6.-planning-fees/fy27-impact-fee-information-sheet.pdf)
   City of Palo Alto · last checked 2026-11-19
13. [City of Palo Alto: FY 2027 Adopted Municipal Fee Schedule, development impact fees with "ADUs under 750 sq ft exempt" notes (PDF p. 77)](https://www.paloalto.gov/files/assets/public/v/1/administrative-services/city-budgets/municipal-fee-schedules/fy-2027-adopted-municipal-fee-schedule.pdf)
   City of Palo Alto · last checked 2026-11-19
14. [Palo Alto Unified School District: School Impact Fees](https://www.pausd.org/about-us/funding/school-impact-fees)
   PAUSD · last checked 2026-11-19
15. [City of Palo Alto: JADU deed restriction agreement process (Nov 15, 2023, PDF)](https://www.cityofpaloalto.org/files/assets/public/v/5/development-services/planning-review/1.-single-family-and-duplexes/jadu-deed-restriction-agreement-process-11-15-2023-one-page.pdf)
   City of Palo Alto · last checked 2026-11-19
16. [Contractors State License Board: check a license](https://www.cslb.ca.gov/)
   State of California · last checked 2026-11-18
17. [City of Palo Alto Open Data: Palo Alto Development Center Permits (Building module export, Dec 2017 to Nov 16, 2026)](http://data.paloalto.gov/dataviews/265480/palo-alto-development-center-permits-mar-2025-nov-2026/)
   City of Palo Alto Open Data · last checked 2026-11-18
18. [City of Palo Alto Open Data: Palo Alto Development Center Permits, current export (record status and status date, updated weekly by the city)](https://data.paloalto.gov/dataviews/265480/palo-alto-development-center-permits-mar-2025-nov-2026/)
   City of Palo Alto Open Data · last checked 2026-11-19
19. [City of Palo Alto Accela Citizen Access: building permit and planning record pages (status, public attachments, plan sets)](https://aca-prod.accela.com/PALOALTO/)
   City of Palo Alto · last checked 2026-11-19
20. [City of Palo Alto PermitView (city GIS permit search: record status, status date and Accela record keys)](https://gis.cityofpaloalto.org/PermitView/)
   City of Palo Alto GIS · last checked 2026-11-19